
Interstate Bridge Replacement Program team proposed a bridge 116-feet high; Coast Guard says it needs to be at least 178 feet
The U.S. Coast Guard recently revealed that any replacement of the existing Interstate 5 Bridge needs to have a vertical navigation clearance (VNC) of at least 178 feet, a significant contrast to the 116-foot height of the bridge the Interstate Bridge Replacement Program (IBR) team members have proposed.
The letter, dated June 17, provided a summary conclusion for Preliminary Navigation Clearance Requirements of the proposed I-5 Bridge replacement.
“The Columbia River System is an extremely important interdependent-multimodal supporting national and international commerce critical to local, national and global economies,’’ wrote B.J. Harris, chief of the Waterways Management Branch, Coast Guard District Thirteen. “Reducing the capability and capacity of the Columbia River System would severely restrict navigation. IBR’s proposed bridge … with its 35% reduction of VNC from 178 feet to 116 feet is contradictory to the U.S. Coast Guard’s mandate from Congress to maintain freedom of navigation on the navigable waters of the U.S. and to prevent impairment to U.S. navigable waterways.
“As new structures are built, navigation clearances should be improved or at a minimum maintained,’’ Harris continued. “Any proposed new bridge should have a VNC of greater than or equal to that of the existing I-5 twin bridges of 178 feet or preferable, unlimited VNC …’’
In his letter, Harris stated that alternative options are available and he even offered an example.
“There are alternative options to accomplish this VNC to include a tunnel or a high-level lift bridge or bascule bridge, which would provide an unlimited vertical clearance,’’ he wrote. “A modern similar successful project is the Woodrow Wilson Bridge over the Potomac River in Washington, DC that was completed in 2009. It is a higher-level double bascule lift bridge on an interstate (I-95) with transit. The added height of the new bridge reduced the number of bascule bridge openings for vessel passage by 76%.’’

At the June 17 Bi-state Bridge Committee meeting, the IBR team indicated that anything higher than 116 feet of clearance for the I-5 Bridge replacement would cause the IBR to have to go to a “moveable span.” Administrator Greg Johnson had indicated that the moveable span could cost $400 million. He further indicated “some things you want to be the biggest . . . but this isn’t one of them,” in reference to trying to design a bridge with a moveable span.
In light of the Coast Guard letter and requirement for 178 feet of clearance, Clark County Today asked Johnson if the IBR will now begin designing a bridge with a moveable span? And, if this significant change would alter the team’s timeline for entering the Supplemental Environmental Impact Statement (SEIS)?
“As the Coast Guard notes, this preliminary determination does not constitute an approval or final agency determination,’’ Johnson said. “The IBR program respects the Coast Guard’s focus on preserving navigation for the nation. While the Coast Guard is specifically charged with addressing the needs of navigation, the IBR program has a responsibility to identify a multimodal solution that not only addresses the needs of navigation but those of all program area users including air, transit, freight, vehicle, and active transportation.
“As new information becomes available, the navigation clearance identified may change,’’ Johnson added. “The Interstate Bridge.Replacement (IBR) program will continue coordinating with the Coast Guard and our other federal and regional partners to identify a solution that best accommodates river navigation while balancing the needs of other modes, including freight, automobile, bicyclists, pedestrians, transit, and aviation. In the next few months, the program will complete a written assessment to analyze the tradeoffs of a higher navigation clearance and a movable span. While the program’s hope is to avoid a lift span bridge option, the program will continue to closely coordinate with the Coast Guard to discuss the trade-offs and mitigation to accommodate river navigation, highway and air needs.’’
Johnson said the IBR team was not surprised by the Coast Guard’s response.
“Given that this preliminary determination from the Coast Guard was an anticipated part of the process, the IBR program does not anticipate an impact to the program timeline,’’ Johnson said. “The program does not anticipate receiving a bridge permit until the 2025/2026 timeframe, so work over the next few years will address program tradeoffs to balance regional needs. The program’s hope is that the upcoming movable span assessment will address current issues, in advance of the submission of the draft environmental documentation. Opportunities to avoid, minimize, or mitigate adverse impacts, such as potential modifications to vessel equipment, will be thoroughly investigated, as needed in the environmental and permitting process.’’
Johnson also offered a link to the Coast Guard preliminary determination which includes a summary memo of the next steps in the process.
The Coast Guard’s statement comes at a time when Johnson is visiting with area government agencies instead of partners seeking an endorsement for the IBR’s Locally Preferred Alternative (LPA). He has already made a presentation to the members of the Vancouver City Council, who are expected to vote on a resolution at a meeting scheduled for July 11. Members of the Clark County Council are also working on a response to the LPA.
In his letter, Harris also stated that in addition to the 178-foot VNC that any side channels from the U.S. Army Corps of Engineers (ACOE) approved main navigation channel/project “would require vertical clearances equal to or greater than 72 feet.’’
“Generally, the Coast Guard does not approve bridge proposals with vertical navigation clearances below the ‘present governing structure’ when the existing VNC has been and is currently needed unless there is a compelling navigational reason to do so,’’ Harris wrote. “The existing I-5 twin bridges are the ‘governing structure’ on the Columbia River west of the Glenn Jackson I-205 Bridge. They are the lowest navigational obstruction (bridge or overhead cable) between the I-205 Bridge and west to the confluence of the Pacific Ocean and the Columbia River.
“Vessels with a VNCR of up to 178 feet have been able to navigate upriver from the Pacific Ocean since 1917, including past the first obstruction at the Astoria-Megler Bridge (with a vertical clearance of 193 feet),’’ he added. “The next four vertical clearance obstructions after the Astoria-Megler Bridge are between river miles 40 and 104 (with clearances ranging from 187 feet to 220 feet). A VNC of less than 178 feet would, for the first time in a century, decrease the present governing structure VNC by as much as 35% (reducing 178 feet to 116 feet). The next upriver VNC obstruction past the current governing structure is the Glenn Jackson I-205 Bridge approximately 6.75 miles upriver with a VNC of 136 feet to 144 feet.”

Harris wrote that “Multimodal Transportation Columbia River access facilitates the movement of products which are too large to truck or ship by rail. On-site barge access accommodates river and ocean-going vessels up to 400 feet in length, and with air drafts up to 178-feet tall. Outside storage capacity near the barge slips allows for unprecedented scale outdoor fabrication/assembly, staging and storage. CBC’s (Columbia Business Center) barge facilities are private and do-it-yourself in nature, eliminating red tape and outside controls and restrictions. CBC has accommodated construction of naval warships, yachts, oil rigs, bridge and dam components, and mass transit infrastructure. Dating back to its origins as a Kaiser shipyard and continuing to this day, the facilities at CBC allowed for prefabrication and special construction methods to efficiently produce products key to US national security and infrastructure. Whether the first occupant, Kaiser Shipyards; current tenants such as Greenberry Industrial, JT Marine, Thompson Metal Fab, or Vigor Industrial; or future tenants, it has always been the case that the vertical navigation clearance requirements of 178 feet under the Interstate 5 bridge have been critical to deliver products to and from markets.”

Also read:
- Citizens have opportunity to provide input on Oregon tollingThe Oregon Department of Transportation will hold two events where citizens can view information about the Regional Mobility Pricing Project.
- Opinion: Interstate Bridge Replacement Program incompetence and deceptionRetired Engineer Bob Ortblad believes a new study of an immersed tunnel by a consultant independent of the IBR must be done.
- Paying more and getting less for transportation in Portland areaTransportation tolling plan sparks outrage as promised freeway lanes disappear, impacting traffic and affordability in the Portland area.
- Washington lawmaker joins bipartisan call for carbon tax overhaul to ease gas painsState Rep. Jim Walsh, R-Aberdeen, is urging legislative action to lower the price at the pump for Washington motorists paying the second-highest gas prices in the nation, including scrapping or modifying the state’s carbon tax.
- Tolling in Oregon still on target to charge for driving former freewaysOregon’s tolling plans face uncertainty as the state indefinitely pauses I-205 projects and grapples with a $3 billion funding gap, impacting commuters between Oregon and Washington.
Sigh…. I am sooooo tired of the current IBR committee telling me what I want and need. And now they’re telling the Coast Guard that they (C.G.) really want and need.
Newsflash… the choo-choo has been consistently voted down by voters. It is agreed that the votes were for “not funding” (vs. “do you want it or not”). But those that would say it was not a valid vote are simply splitting fine hairs. When given the opportunity, voters have consistently said NO to the choo-choo.
Newsflash… if you think that the affected upriver industrial businesses are going to now be bought off for about a total of $400 million, then I’ve got a bridge in Brooklyn to sell you. How about $400 million EACH, or more!? They’ve learned their lesson and realized the impact that not being able to go downstream, under the bridge, will have on their businesses.
And we’re still not gaining additional lanes or faster transit times. But, hey, we will be paying $_x_ per crossing for the privilege of sitting in the same traffic as we are at the present time.
This really IS just the CRC v2.0. I’m looking forward to its demise. Maybe then someone in authority will say “hey, how about we build a 3rd bridge.”
Susan — your comments are spot on. Three years ago, I offered the following comments and history, to the members of our RTC Board of Directors. They continue to ignore what numerous past studies and community surveys have demanded.
“Do you accept 40 years?
At last month’s Board meeting, (June 2019), an RTC staffer told us it takes 40 years to plan and create a new cross-river transportation corridor with a new 3rd bridge. Do you believe that? Is that an acceptable answer to this board?
In Minneapolis, the I-35 bridge was replaced in ONE year!
In the Portland metro area, both I-5 and I-84 were planned for in the mid 1950’s. In the late 60’s and early 70’s, I-205 was created in under 2 decades. At the same time, there were plans and routing created for a western bypass. Here is the map of that plan.
In 1977-79, a Washington legislature study found: “Without a new crossing, the I-5 bridge would be overloaded 30% beyond its capacity by the year 2000.” Their report included 5 possible locations for a 3rd bridge. (Here’s their map).
A 1979 Clark County Comprehensive Plan showed extending 179th St. across the Columbia River to US 30 near Scappoose.
A 1980 WA legislature study concluded: “travel demand on the I-5 corridor beyond the year 2005 will require additional facilities”.
A 1980 OR & WA Governor’s Task Force said “a 3rd bridge would not increase the capacity for interstate travel unless it were accompanied by a new corridor north and south of the Columbia River”. The technical analysis concluded that “the region would not have to revisit the question of additional river crossings until 1990.”
Additionally, that same study recommended “bottlenecks north and south of the I-5 bridge were the limiting factors and not the bridge itself”.
The 1980 Bi-State Study forecast 185,000 cross-river daily vehicle trips in 2000. A 1988 study show I-205 traffic had already exceeded the 2000 forecast. Today WSDOT reports roughly 310,000 daily crossings.
That 1988 study also discussed the benefits of TWO new bridge crossings, one west of I-5 and one east of I-205.
Finally, your own 2008 RTC “Visioning Study” offered FOUR options for two new bridge crossings and transportation corridors.
What’s it going to take for this Board to show some leadership? When will the RTC take action on a 3rd bridge?
The NEED for additional bridges and transportation corridors has been identified for the past HALF century! If the RTC staffer was correct about 40 years, you’ve owed citizens a completed 3rd bridge for a decade!
Citizens are BEGGING for a 3rd bridge and traffic congestion relief.
If the Coast Guard insists on a raisable bridge with 178 feet clearance, then we don’t need a new bridge. The one we now have meets the Coast Guard requirement. The whole point of the IRB is to do away with causing traffic chaos by raising the bridge. The IRB has a good, workable solution to the river traffic problems created by the lower 116 feet clearance in the new bridge. Either accept the 116 feet design or cancel the new bridge.
Unfortunately, the whole point of the IRB is NOT to do away with causing traffic chaos by raising the bridge. That was just one of the justifications for the new bridge. The new bridge was also to have better seismic protection, better shoulder space, and better merges from Janzen Beach.