The latest Vine route, scheduled to open in 2027, will run from the Waterfront in downtown Vancouver to Washington State University Vancouver’s campus via Highway 99
Paul Valencia
Clark County Today
Leaders from C-TRAN, Washington State University Vancouver, and special guest Butch the Cougar gathered Wednesday to celebrate The Vine.
“It is a pleasure to be here today to mark this major step forward for our region, for our transit system, and for our campus community,” said Sandra Haynes, interim chancellor of Washington State University Vancouver.
She and other guest speakers stood on a podium that was on the ground that will eventually become the northernmost station on The Vine on Highway 99 — on the campus of WSU Vancouver.
Wednesday marked the groundbreaking for what will become a 9-mile north-south route from the campus in Salmon Creek to Highway 99, to downtown Vancouver and the Waterfront.
“WSU Vancouver is committed to being an institution of access, excellence, and service,” Haynes said. “For many students, and many potential students, access to higher education starts with simple but essential: the ability to get to campus.
“Today is such an important moment for WSU Vancouver. The new Vine on Highway 99 will bring fast, frequent, and reliable service to WSU Vancouver, connecting our campus to neighborhoods across Clark County.”

This will be the third Vine route for C-TRAN’s bus rapid transit system, following Fourth Plain Blvd. and Mill Plain Blvd. routes.
BRT “is the crown jewel of our community,” said Adrian Cortes, state senator for the 18th Legislative District.
“This project represents a milestone for all of Clark County, not just the city of Vancouver or Highway 99,” said Molly Coston, chair of the C-TRAN Board of Directors who represents Washougal on the board. “Having a strong transportation network strengthens smaller cities like mine. C-TRAN has always recognized this.”
Tod Tapani, vice president of operations for Tapani Inc., the contractor for the project, told C-TRAN leaders that his company is “proud to take your vision and turn it into something.”
Tapani was the contractor for the two previous Vine projects.
Leann Caver, chief executive officer of C-TRAN, noted that The Vine is not just a way for more efficient bus services.
“This project will deliver meaningful infrastructure and real improvements,” she said, including new sidewalks and pedestrian crossings.
There will be 32 new stations along the 9-mile route.
“It will make Highway 99 a safer, more accessible corridor,” Caver said.
C-TRAN’s timeline on its website calls for The Vine on Highway 99 to open in 2027.
Also read:
- Opinion: ‘If you tolerate lies and dishonesty from the government, you’re guaranteed more’Lars Larson criticizes state officials for refusing to disclose updated cost estimates for the Interstate Bridge Replacement project, arguing that a lack of transparency guarantees further government dishonesty.
- Maneuver to shore up WA’s transportation budget could be reversedWashington lawmakers are weighing whether to reverse a planned sales tax transfer to transportation as they confront a looming operating budget shortfall.
- Rep. John Ley issues statement after I-5 Bridge replacement meeting yields few answersRep. John Ley criticized the IBR Program for failing to provide updated cost estimates or key design decisions following a recent legislative oversight committee meeting.
- Opinion: Too deep to drive – flooded roadsDoug Dahl explains why even shallow water on roadways can be dangerous for drivers and outlines the risks of hydroplaning and driving through floodwaters.
- C-TRAN takes no action on Board Composition Review Committee’s directiveAfter a long executive session, the C‑TRAN board took no action on a 4‑3‑2 board composition proposal that has divided Vancouver, Clark County and the small cities.