Payments totaling $140 million will only be made if the Coast Guard permits a fixed-span bridge and construction begins
VANCOUVER – Oregon and Washington officials believe they have moved one step closer to replacing the Interstate Bridge after signing agreements with the four river users identified as being affected by a proposed fixed-span bridge across the Columbia River.
These agreements paved the way for the Oregon Department of Transportation (ODOT) and Washington State Department of Transportation (WSDOT) to submit an updated Navigation Impact Report on behalf of the Interstate Bridge Replacement (IBR) Program to the U.S. Coast Guard proposing a fixed-span bridge of 116 feet vertical navigation clearance. Officials believe this is a critical milestone towards receiving a bridge clearance permit to replace the 108-year-old Interstate Bridge connecting the two states.
“This project is critical for Washington state,” Washington Governor Bob Ferguson said. “A fixed span removes the only stoplight on I-5 between Canada and Mexico, supports our economy and has broad consensus across many stakeholders. Reaching agreement between all four river users for the first time shows a clear path forward.”
IBR officials claim the proposed 116-foot high replacement fixed-span bridge would continue to provide access for 99% of river traffic, while removing the stoplight on Interstate 5 to improve safety and reliability for roadway commerce, vehicles and transit. The impacts to identified river users have now been mitigated through the agreements. IBR and transportation officials claim there is strong regional and community support that a fixed-span bridge would best address the needs of all users.
“The IBR Program has demonstrated that a fixed-span bridge is the best solution for the largest number of users for the future transportation reliability and safety the region needs,” Oregon Governor Tina Kotek said. “I appreciate Governor Ferguson’s partnership in making sure we can get to the next milestone for the new bridge.”
IBR officials claim a new movable span would perpetuate the same issues travelers experience with the existing movable bridge, including travel delays, reduced freight mobility and a high crash rate. Based on past estimates without accounting for inflation, construction of a movable span bridge would cost approximately half a billion dollars more (in 2022 dollars) than a fixed span and would cost $1 million more per year to operate and maintain. By comparison, these agreements totaling $140 million represent a more cost-effective solution to advance the IBR Program to construction according to proponents of the proposed bridge replacement. Payments will only be made if the Coast Guard permits a fixed-span bridge and construction begins.
River user agreement process
The IBR Program conducted extensive analysis and outreach to better understand the potential impacts to river users resulting from a fixed-span bridge with 116 feet of clearance. River users were identified as businesses that own or operate vessels that navigate the Columbia River, or manufacture products shipped under the Interstate Bridge. The IBR Program engaged independent experts to assess these potential impacts based on industry data and information provided directly from river users.
Comprehensive valuation processes were conducted to analyze current and projected business conditions using a thorough review of operations, vessel characteristics, site capabilities, employment data, financial statements and future revenue forecasts. It also considered potential business losses resulting from lost market opportunities and potential effects from changes to river users’ operations. An additional independent assessment was conducted, which validated that the process supporting negotiations was appropriate and adequate.
These agreements are intended to support the continued operation of these businesses at their current locations and in the region and demonstrate to the Coast Guard that the Program has addressed potential impacts.
Next steps to USCG revised decision on fixed or movable bridge
Next steps include the Coast Guard reviewing the information provided in the Program’s updated NIR. The Coast Guard will then hold a 30-day navigation comment period for river users and review those comments. At the conclusion of these steps, the states are hopeful that the Coast Guard will issue a revised Preliminary Navigation Clearance Determination for a fixed-span bridge. The Coast Guard’s decision is expected in early 2026.
Following this process, the Program’s federal lead agencies in the environmental review process – the Federal Highway Administration and Federal Transit Administration – can issue an Amended Record of Decision approving the Program to move into construction.
Also read:
- POLL: After hearing state leaders describe the I-5 Bridge as vulnerable in an earthquake, what is your reaction?State and local leaders describe the I-5 Bridge as structurally at risk but recommend drivers continue crossing it while complex replacement plans unfold.
- WA and OR scale back I-5 Bridge ambitions as cost balloonsA $14.4 billion price tag prompts Washington and Oregon leaders to delay portions of the I-5 bridge project and prioritize just the main spans.
- Letter: ‘Now we have Engineer Bob telling us the I-5 Bridge needs replacing because it is built on shifting sand with wooden structures’Amboy resident Thomas Schenk critiques Democrat leadership, tax policies, and the addition of light rail to the I-5 Bridge, while urging Republican voters to participate more in midterm elections.
- The I-5 Bridge is vulnerable to collapse, but apparently not that vulnerableState leaders and Vancouver’s mayor warn about bridge safety, but insist it’s safe enough for daily use as they focus on moving forward with a costly replacement including light rail—despite decades of public resistance.
- Opinion: ‘This is not the best and most efficient use of the taxpayers’ funds’Ken Vance critiques the announced $14.4 billion I-5 Bridge replacement, questioning funding gaps, the insistence on light rail, unaddressed congestion, and transparency from state officials.