Bob Ortblad says new $13.6 billion I-5 Bridge replacement cost estimate is probably too low by billions
Editor’s note: Opinions expressed in this letter to the editor are those of the author alone and may not reflect the editorial position of ClarkCountyToday.com
The Willamette Week recently reported that for six months, the Interstate Bridge Replacement Program (IBR) hid an estimate that doubled the project cost from $6 billion to $13.6 billion. This shocking $13.6 billion estimate is probably too low by billions.

The SR 520 Portage Bay Bridge and Lid project was bid in November 2023 at $1.4 billion and was 70% above the engineers’ estimate. Skanska, the design-build contractor, attributes about 80% of this cost — approximately $1.1 billion — to the new bridge itself. Notably, the Portage Bay Bridge is nearly the same length as the proposed I-5 Bridge design and is supported by similar large-diameter drilled shafts. Furthermore, this bridge is being constructed in a shallow, weather-protected cove that is only 10 feet deep.
In contrast, the design for the I-5 Bridge is twice as large and situated in a more challenging location affected by tides, currents, and strong winds. The IBR bridge design is more than twice as wide (239’ vs. 114’), with piers four times higher. (100’ vs. 25’) The bridge also has twice the number of drilled shafts. (96 vs.50) The IBR shafts are also longer (250’ vs. 200’) and have a higher probability of hitting cobbles and boulders as they are drilled.
The IBR needs a 200,000 pound oscillator to drill 10-foot diameter shafts 250 feet through unpredictable Columbia River sand, cobbles, and boulders. Skanska is using a more mobile, less expensive vibratory hammer that is ten times lighter than IBR’s oscillator. The bottom of Portage Bay is a predictable soft sediment; over a hundred shafts have been completed just east in Montlake and Lake Washington.
In 2012, the Columbia River Crossing’s total estimated cost was $3.5 billion. The 250-foot, 10-foot diameter shafts were estimated to cost $1.25 million each, $5,000 per foot. A $4.2 million test shaft was drilled on Hayden Island by Malcolm Drilling, and it failed on the first attempt.

The current IBR estimated cost of $13.6 billion is a 288% increase from the CRC’s $3.5 billion, but the IBR estimated cost of drilled shafts ($129,586,650) has only increased 17% from $5,000 to $5,845 per foot. If a 288% increase is applied to drilled shafts, their cost will balloon from about $129 million to $632 million.
How many items in IBR’s current $13.6 estimate need to be doubled or tripled?
The SR 520 Portage Bay’s Bridge cost is $1.1 billion. By every measure, the IBR bridge design is twice as large and is a much more difficult construction site, therefore it should cost about twice as much, $2.2 billion. ($3.3 billion risk-adjusted). However, IBR’s base cost bridge estimate is only $1.1 billion. (not including approaches).
An Immersed Tunnel alternative was fraudulently disqualified by the IBR. An Immersed Tunnel needs no drilled shafts; it is supported by buoyancy. A tunnel could save about $600 million without shafts, $140 million by not bribing upstream businesses, and $300 million by not demolishing current bridges. The tunnel can also be built faster with less environmental impact.
Bob Ortblad MSCE, MBA
Seattle
Also read:
- Letter: Interstate Bridge Replacement $13.6 billion estimate is too low! Bob Ortblad argues the Interstate Bridge Replacement Program’s $13.6 billion cost estimate understates the true expense, citing comparable projects, construction challenges, and engineering assumptions.
- Opinion: ‘The drama and the waste of taxpayer money continues’Rep. John Ley outlines his objections to the approved fixed-span I-5 Bridge design, citing cost concerns, engineering standards, funding uncertainty, and opposition to light rail and tolls.
- Coast Guard approves fixed-span design for new Interstate BridgeThe U.S. Coast Guard has approved a fixed-span design for the new Interstate Bridge, clearing a major hurdle for the Interstate Bridge Replacement project.
- Opinion: When fast feels slowDoug Dahl explains why drivers often misjudge their speed, especially when using cruise control or transitioning from freeway to city streets.
- Opinion: WSDOT secretary and I ‘obviously have very different definitions for the term cost-effective’Clark County Today Editor Ken Vance sharply criticizes WSDOT Secretary Julie Meredith’s defense of the Interstate Bridge Replacement project, arguing the escalating cost estimates undermine claims the project is cost-effective.







Oh, Bob, don’t confuse the issue with logic and facts! The empress-mayor annie ogle has spoken… the “little people” of SW Wash. will be given a high-toll bridge.
When does the recall petitions get started, for the empress-mayor and other mis-leading clowncil members in Vancouver and in Clark County?
The city doesn’t care about costs as long as there is a bike trail which nobody will use and light rail which nobody else wants.