🎧 I-5 Vancouver: Smoother Roads Coming This Summer
Nighttime work keeps traffic moving as crews smooth out I-5
VANCOUVER – Travelers on southbound Interstate 5 in Vancouver will soon experience a smoother ride as crews take the next step toward fixing rough and bumpy roads.
On Monday, May 4, Washington State Department of Transportation contractor Kerr Contractors Oregon LLC started work to repair the driving surface along southbound I-5 between Northeast 179th Street and the I-5/I-205 split. This work is weather dependent and will continue through the summer, with breaks during major events.
Once complete in late summer 2026, crews will remove the “Rough Road” signs between Northeast 179th Street and I-205.
Crews will use a method called “crack, seat and overlay” to rebuild the road. First, they use a heavy machine to break the old concrete into smaller pieces. Then they press those pieces down to create a solid base. Finally, they add four new layers of asphalt, each about 2 inches, on top to create a smoother, longer-lasting surface.
“This stretch of I-5 has been a rough ride for years,” said WSDOT Project Engineer TJ Prendergast. “This work will help create a smoother road for travelers.”
This method allows crews to repair more roadway at once while reducing costs and effects to travelers.
What to expect
- Occasional shoulder closures and up to three-lane closures in the work zone.
- Some full closures of I-5 and I-205 near the split, along with on-ramp closures. Most full closures will take place at night or on weekends to reduce impacts to travelers.
- Weekend lane closures with two lanes open on I-5 during the day.
- Travelers should plan for heavier traffic and possible delays of up to 6 miles on southbound I-5.
- Work will pause during major events, including the Clark County Fair, to help reduce effects to travelers and local traffic.
Recent improvements
This 2.2-mile stretch of southbound I-5 was built in 1969 using concrete panels. Many of the roughly 8,400 panels are more than 50 years old and are worn down, creating a rough and uneven ride.
From 2022 to 2025, crews focused on the “worst of the worst” sections, replacing about 180 panels along I-5 and I-205 near the split. While these efforts helped improve conditions, some roughness remains.
Looking ahead
Crews will also address the stretch of I-5 just north of the crack, seat and overlay project, between Northeast 179th Street and Ridgefield.
This summer, crews will replace the most damaged panels. In 2027, they will return to complete the full crack, seat and overlay work.
This stretch of I-5 is part of many daily trips, from early morning commuters heading to work and local travelers running errands to freight trucks moving goods through the state.
Real-time travel information is available from the WSDOT mobile app and the WSDOT Travel Center Map.
Also read:
- Clark County Sheriff’s Office investigating deadly stabbing in Battle GroundA man died and a woman was hospitalized after a stabbing near NE 117th Ave and NE 244th St in Battle Ground.
- Charter Review Commission members grow increasingly frustrated with overreach by county executivesCommissioners Donnelly, Gasque, and LaBrant accused county staff and Auditor Kimsey of tilting the charter amendment process.
- US Senate blocks Trump’s SAVE America ActThe 48-50 Senate vote fell far short of the 60 needed to overcome a filibuster and advance Trump’s voter ID bill.
- VIDEO: Battle Ground mayor stands by pro-ICE, anti-Antifa proclamationsBattle Ground Mayor Eric Overholser signed proclamations on ICE and Antifa, drawing national media attention to the city of 23,000.
- WPC Forum asks if Washington is a state that is friendly for businesses and workersPanelists clashed over the new millionaire’s tax, minimum wage, retail theft, and AI’s threat to the workforce.